The Wisconsin Department of Transportation (WisDOT) is proposing a resurfacing and improvements project along approximately 1.1 miles of WIS 67 (Lincoln Street) between I-43 and Walworth Street, in the city of Elkhorn, Walworth County.

Proposed Improvements

  • Mill and resurfacing about 1.1 miles of roadway, including pavement repairs.
  • Replace traffic signals at the WIS 67 (Lincoln Street) and Geneva Street intersection.
  • Update curb ramps to meet ADA standards
  • Box culvert maintenance
  • Coordinate with Wisconsin & Southern Railroad to replace crossing pavement, signals, and gates.

Proposed Traffic Impacts

Traffic impacts are still being determined. Additional information will be posted here when available.

Schedule

This project is in the design phase with construction tentatively scheduled for 2031. Work may be advanced to 2029, if funding becomes available. If you have any comments or questions about this project, please contact the project representatives listed below.

Contact Information

Bob Bellin, P.E.
WisDOT Project Manager
(262) 521-4405
Robert.Bellin@dot.wi.gov

Chris Verhyen
WisDOT SE Region Communications
(262) 548-8757
Chris.Verhyen@dot.wi.gov