This page outlines the proposed schedule for the Oregon/Jackson Street Bridge Study and any potential improvement project construction. All schedules are subject to change.
Current (this year)
- WisDOT received approval on our environmental document in February 2024 that includes a high-level fixed bridge on a partially offset alignment, as our preferred alternative.
Future (next year and beyond)
- 2025-27: Final design phase
- 2025-27: Real estate acquisition
- 2027-28: Utility relocations
- 2028: Construction begins on selected alternative
- 2029/30: Construction complete
Past (anything prior to today)
- February 2024 - Environmental document approved
- June 2022 - Oshkosh City Council votes 7-0 in favor of high level fixed bridge
- March 2022 - Oshkosh City Council workshop
- April 2022 - PIM #3 for environmental study
- Summer 2021 - WisDOT resumes environmental study
- Late 2017 - WisDOT suspends environmental study
- May 2017 - Oshkosh City Council votes 4-3 in favor of
Alternative F
- January 2017 - Oshkosh City Council workshop
- October 13, 2016 –
Public involvement meeting (PIM) #2 for environmental study
- 2016/2017 – Study discussion and coordination with city of Oshkosh officials
- April 27, 2016 – PIM #1 for environmental study
- Fall 2015 – Environmental study began