Location
WIS 29, County H to Purple Martin Lane Eastbound, Marathon County
Project Overview
The proposed project will replace the existing WIS 29 eastbound pavement and asphalt shoulders, including subgrade and base course materials, between approximately 2,100 feet west of County H and approximately 2,000 feet west of Purple Martin Lane.
Traffic Impacts
WIS 29 will remain open to traffic. The project will utilize crossovers which will allow for eastbound traffic to crossover and travel on westbound WIS 29, where one lane will be maintained for each direction. Side road approaches to WIS 29 may be constructed in stages to allow for cross traffic or use a short-term closure and detour to an adjacent sideroad crossing during construction. The County H interchange will have ramp closures to complete ramp connections to WIS 29.
Real Estate
No real estate acquistion is anticipated
Schedule
- Local Officials Meeting: Early June 2025
- Public Involvement Period: June 21, 2025 to July 21, 2025
- PSE: May 1, 2026
- Construction scheduled for 2027
Public Involvement
A public involvement period is being held. Please review the materials below and provide comment by
July 21, 2025.