The Wisconsin Department of Transportation (WisDOT) is seeking public input on a proposed resurfacing project on WIS 70 from County B West east of Spooner in Washburn County to WIS 27 North northeast of Stone Lake in Sawyer County.
The public can go to the project
website, review a presentation, handout and construction overview map and use the form to submit comments by May 2 by:
- Email: Kyle.McLean@dot.wi.gov
- Mail: Wisconsin Department of Transportation
718 W. Clairemont Ave.
Eau Claire, WI 54701
Attn.: Kyle McLean
The existing pavement is showing signs of deterioration. To address this and other issues, WisDOT is proposing to:
- Remove two inches of the existing pavement and placing two inches of new pavement over the roadway
- Adjust and/or replace guardrail sections
- Upgrade sidewalk curb ramps to meet Americans With Disabilities Act standards
- Repair or replace culverts
- Place new pavement markings
During construction, WIS 70 will remain open to traffic, but motorists will encounter single-lane closures controlled by flagging, along with shoulder closures.
Construction currently is scheduled 2032, but work could occur as early as 2029 if funds become available.
Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.
For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region:
For more information, contact:
Christena T. O'Brien, Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471,
christena.obrien@dot.wi.gov