Overview
Built in 1975, the Yellow River Bridge on US 63 in Spooner is showing signs of deterioration. To address that, the Wisconsin Department of Transportation is proposing to:
- Overlay the bridge deck with concrete
- Make concrete surface repairs to bridge abutments and parapet
- Replace concrete approach slabs
- Pave the roadway with asphalt on both sides of the structure
- Complete work to improve drainage adjacent to the bridge
- Replace guardrail on the west side of US 63
- Replace pavement markings
In This Together
WisDOT has developed the In This Together program to provide tips and tricks to business owners on how to navigate construction projects. For more information:
Schedule
Construction currently is scheduled for 2028.
Traffic Impacts
Construction on US 63 will be staged. During one stage, traffic will be restricted to a single lane on the west side of the bridge controlled by temporary traffic signals, and during the other, one lane of traffic will be maintained in both directions on the east side of the structure.
Public Involvement
WisDOT held a public involvement meeting on this project on Feb. 5, 2025. Meeting materials can be viewed here:
Contacts - Updated
Heath Hagner
WisDOT Northwest Region Consultant Project Manager
(920) 434-2128
Heath.Hagner@ISGInc.com
Nick Pitsch
WisDOT Northwest Region Project Supervisor
(715) 392-7976
nicholas.pitsch@dot.wi.gov
Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 715-828-9471
christena.obrien@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Northwest Region, Superior Office
1701 N. 4th St.
Superior, WI 54701
(715) 392-7925, (800) 590-1868
nwr.dtsd@dot.wi.gov