Douglas County: US 2/53, Superior to Wentworth

Location

The project is on US 2/53 from 53rd Avenue East in the city of Superior to County C in the town of Amnicon, all in Douglas County.

Overview

The pavement and culverts carrying storm water on US 2/53 are showing signs of deterioration as is the pavement at Rest Area 23 along the eastbound lanes. To address these, the Wisconsin Department of Transportation is proposing the following:

  • On US 2/53 in both directions:
    • Repairing concrete pavement, including making concrete joint repairs and replacing concrete pavement panels
    • Milling existing asphalt shoulders and overlaying shoulders with new asphalt
    • Milling and overlaying side road connections and the WIS 13 ramps
    • Installing shoulder rumble strips and gravel shouldering
    • Replacing culvert pipes
    • Repairing roadway slopes or embankments that have been eroded
    • Repairing the box culvert at Bear Creek
    • Replacing the large signs along US 2/53
    • Replacing right-of-way fencing along portions of the project
    • Repairing or replacing guardrail
    • Updating pavement markings to current standards
  • At Rest Area 23:
    • Replacing existing exterior facility lighting
    • Upgrading and modernizing pedestrian curb ramps
    • Replacing select panels of sidewalk
    • Cleaning joints and cracks on the existing concrete pavement entrance and exit to the facility as well as perimeter parking lot
    • Repairing existing concrete pavement or replacing concrete pavement panels as necessary
    • Repairing curb and gutter in spot locations
    • Overlaying existing concrete pavement with asphalt at entrance and exit to the facility as well as perimeter parking lot
    • Razing the existing maintenance garage and constructing a new garage and garbage area.
    • Adding additional semi-truck parking by increasing size of existing parking
  • At the Superior Safety and Weight Enforcement Facility (SWEF):
    • Upgrading and modernizing pedestrian curb ramps
    • Refreshing pavement markings

Schedule

Construction currently is scheduled for 2028 and 2029.

Traffic Impacts

During construction:

  • US 2/53 will remain open to traffic; however, north- or southbound lanes may be closed, crossovers may occur, and traffic may be limited to one lane in each direction.
  • Delays should be expected when traveling the work zone, especially during commuting hours.
  • Rest Area 23 repairs may require temporary closure of the facility.

Public Involvement

WisDOT is seeking public input on the proposed project. Please review the following:

Comments can be submitted through Jan. 30, 2026, by:

Contacts

Nick Maki
WisDOT Northwest Region Project Leader
(715) 492-1449
nicholasd.maki@dot.wi.gov

Stephanie J. King
WisDOT Northwest Region Project Manager
(715) 392-7874
stephanie.king@dot.wi.gov

Matt Van Natta
WisDOT Northwest Region Project Supervisor
(715) 392-7966
matthew.vannatta@dot.wi.gov

Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Northwest Region, Superior office
1701 N. 4th St.
Superior, WI 54880
(715) 392-7925, (800) 590-1868
nwr.dtsd@dot.wi.gov