Location
WIS 22 at the Labutzke Channel Tributary between Shawano to Gillett in Shawano County
Project Overview
WisDOT is proposing to improve 0.125 mile of WIS 22. The purpose of the proposed project is to address the deteriorated structure over the unnamed tributary to the Labutzke Channel.
Traffic Impact
During construction, WIS 22 will be closed at the bridge, and traffic will be detoured along WIS 55, WIS 29 and WIS 117.
Real Estate
Additional right of way will be required for this project. Small areas of acquisition will be required in all four quadrants of the structure and along the existing spillway.
Rights of Landowners Under Wisconsin Eminent Domain Law [Wis Stats 32.05]
Schedule
- Local Officials Meeting: Nov. 14, 2024
- Public Involvement Meeting: Dec. 5, 2024
- Final Plans: Aug. 1, 2026
- Construction currently scheduled for 2027
Public Involvement
A public involvement meeting was held. The following information was presented:
Additionally a public involvement comment period was held. The following information was presented: