Location
WIS 187, Outagamie County Line to WIS 156, Shawano County
Project Overview
Proposed improvements include 2-inch asphalt mill and overlay, culvert replacements, pave existing gravel shoulders with asphalt and pavement marking.
Traffic Impacts
During construction, WIS 187 will be open under single lane closures with flaggers. Culvert replacement will require full closure with a detour using WIS 54 to WIS 47 to WIS 156. Local, business and emergency access will be maintained. However, temporary driveway closures will be necessary will construction is occurring directly in front of the driveway. WisDOT will contact homeowners and businesses in advance before closing a driveway.
Real Estate
Minor real estate in the form of temporary easements, permanent easements or fee may be required for culvert replacements throughout the project limits.
Project Schedule
Local officials meeting:
- Public involvement: Aug. 14 to 28, 2024
- Preliminary plans: November 2024
- Real estate negotiations: TBD
- Final plans: February 2027
- Construction currently scheduled Spring 2028
Public Involvement
A public involvement period was held. The following information was presented: