Project Overview
The project will include replacing the asphalt pavement. The project will also add paved shoulders from County GG to County G.
Traffic Impacts
Motorists will encounter single-lane closures with flaggers during construction
Real Estate
No real estate acquisition is anticipated
Project Schedule
- Public Involvement period: August to September, 2024
- Final plans and documents: May 2026
- Construction is currently scheduled for 2027