Location
US 8, Gatewood Heights Road to N Rifle Road, Lincoln and Oneida Counties
Project Overview
The existing pavement along this segment of US 8 is exhibiting signs of deterioration. Additionally, some culverts were found to be in poor condition. This project involves removing the existing pavement and replacing with a new asphalt surface. Deficient culverts will be cleaned or replaced. A retaining wall east of Wausau Road will receive minor repair work.
Traffic Impact
Traffic will be managed with single lane closures with flagging operations during construction. Motorists can expect minor delays. Any detour route which may be needed for the culvert replacements is being evaluated.
Real Estate
Minor temporary limited easements may be needed to accommodate culvert replacements.
Project Schedule
- Local officials meeting: October 2024
- Public Involvement: November 2024
- Final Plans: May 2026
- Construction currently scheduled for 2027
Public Involvement
A public involvement period was held. The following information was presented: