Release date: August 3, 2026
To invest in Wisconsin’s transportation system, Governor Evers has approved a $9.1 million resurfacing and improvement project along WIS 164, from Swan Road in Pewaukee to County VV (Main Street) in the village of Sussex. Payne & Dolan is the prime contractor for the project. Construction is scheduled to begin on Monday, August 10.
Improvements include:
- Resurface WIS 164 within project limits
- Update curb ramps to meet Americans with Disabilities Act (ADA) standards
- Replace signals at Swan Road, Lisbon Road, and County VV (Main Street)
Traffic Impacts:
WIS 164 will remain open to one lane of traffic in both directions. Motorists can expect short-term closures at intersections and side roads for resurfacing work.
Local access will be maintained to businesses and residences.
Schedule:
This project will be completed in two (2) stages:
- Stage 1: Swan Road to County K (Lisbon Road).
- This work is scheduled for completion in fall 2026.
- Stage 2: County K (Lisbon Road) to County VV (Main Street)
- This work will begin in spring 2027 and be completed by fall 2027
All work is weather dependent and subject to change.
For more information, contact:
Chris Verhyen
WisDOT Southeast Region Communications Manager