Release date: July 15, 2025
To invest in Wisconsin’s transportation system, Governor Evers has approved a $4.4 million resurfacing and improvement project along I-43/94 in Milwaukee County. LaLonde Contractors, Inc. is the prime contractor for the project. Work is scheduled to begin July 21.
Improvements Include:
This project will resurface and make various improvements to multiple ramps to/from I-43/94 between the Mitchell Interchange and the Marquette Interchange. Ramps to receive improvements include:
- Howard Avenue ramps
- Holt Avenue ramps
- Lapham Boulevard ramps
- National Avenue and 6th Street ramps
Additional project improvements:
- Partial deck replacement on Howard Avenue bridge over I-43
- Bridge deck overlay on Lapham Boulevard and Howard Avenue bridges over I-43
Traffic Impacts:
Motorists can expect overnight ramp closures for paving operations and daily lane closures for intersection work and bridge deck overlays.
Northbound I-43 exit ramp to Holt Avenue to close for approximately 30 days for pavement replacement.
Multiple overnight closures of I-43 and Howard Avenue bridge for critical bridge operations.
Additional ramp and lane closures will take place as needed. Closures of consecutive ramps will be avoided.
Schedule:
This project is scheduled for completion by late 2025. All work is weather dependent and subject to change.
Visit the project webpage at:
https://projects.511wi.gov/43ramps/
For more information, contact:
Chris Verhyen
WisDOT Southeast Region Communications Manager
(262) 548-8757,