Date: July 1, 2026
(Kohler WI) - The Wisconsin Department of Transportation (WisDOT) Northeast Region reminds motorist construction begins on Monday, July 6 on 8.9 miles of WIS 28 from WIS 57 in the town of Lyndon to County A in the village of Kohler in Sheboygan County, Wisconsin. Work begins at 6 a.m., Monday, July 6, 2026, and finishes in late October 2026.
Traffic Impacts
- WIS 28 at the Onion River Tributary located 0.25 miles southwest of the WIS 28 and County N intersection will close at 6 a.m., Monday, July 6 until late summer.
- WIS 28 detour route will utilize WIS 57 and County U
- The roundabout intersection of WIS 28 and WIS 32 will close for 10 days in September for curb and gutter replacement and paving operations.
- WIS 28 detour will utilize WIS 57, County V, and I-43
- WIS 32 detour will utilize WIS 23, I-43, and County V
Project Overview
This is a bridge replacement and resurfacing-level project. Project improvements include:
- Removing the deteriorated culvert structure at the Onion River Tributary located 0.25 miles southwest of the WIS 28 and County N intersection and replace it with a bridge structure
- Milling 4” of deteriorated pavement surface, and overlay will 4” of new asphalt pavement
- Widening the paved shoulder from 3’ to 5’
- Replacing the truck apron, curb and gutter in the roundabout at WIS 28 and WIS 32
- Replacing aging guardrail
- Providing centerline and shoulder rumble strips
For more information
Please see project information, maps, exhibits, and displays online to learn more about this project.
For more information, please contact Missy Kok or Mark Kantola