WIS 23, Montello to Packwaukee

Location

WIS 23, between 8th Court and Morningside Court, town of Packwaukee and town of Montello

Overview

This is a pavement replacement project. Culverts in poor condition will also be replaced within the project limits.

Traffic Impacts

Single lane closures with flagging operations will be utilized during construction. Construction is anticipated to take two months to complete.

Public Involvement

Residents and businesses within the project limits have been contacted via mail.

Schedule

Local officials meeting: April 2021

Public involvement: July 2021

Complete project design: 2023

Construction: 2024