US 2/WIS 13 Intersection Improvement - Schedule

For more information on public information meetings (PIM), hearings and other public activities, visit Public involvement.

Current

  • Apr. 23, 2012 - Construction started

Future

  • Sept. 2012 - Construction scheduled to be completed

Past

2011

  • Dec. 13, 2011 - Project bid letting
  • Jul. 1, 2011 - Final design completed
  • Mar. 8, 2011 - Initial project letting
    • Due to bid prices that were significantly higher than the construction costs Wisconsin Department of Transportation (WisDOT) had anticipated, WisDOT decided not to award the bid this year.
    • Because of this, the roundabout project will not be constructed in 2011 as originally planned. WisDOT reevaluated the design of the roundabout and made modifications to the design to help reduce the construction cost.

2009

2008

  • May 14, 2008 - PIM
  • Jan. 23, 2008 - Meeting with Bayfield County officials


US 2/WIS 13 intersection.

Related information

Roundabouts

Life of a highway project

 


DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey