Location
WIS 101, South Sumac Lane to WIS 70, Portage County
Overview
The asphalt pavement along WIS 101 is showing signs of deterioration. The proposed project will involve a 2-inch mill and new overlay. Additionally, several culverts will be replaced and adjacent guardrail will be replaced as necessary.
Traffic Impacts
The project will include temporary single-lane closures and lane shifts near the work areas during construction. Construction flaggers will direct traffic while construction is ongoing. A detour route is not anticipated at this time. The public will be notified in advance if a detour becomes necessary.
Real Estate
No real estate acquisition is expected
Schedule
- Local officials meeting: March 2024
- Public involvement mailing: March/April 2024
- Complete project design: May 2026
- Construction currently scheduled to begin: Summer 2026